Hello AKPT
I was creating material Master record under T code 'MM01"
I did the following steps in MM01:-
Material: RM9091
Industry: Machanical
Material type: Raw material
Then I select the views:-
Basic data1
Purchasing
MRP1
MRP2
Accounting 1
costing 1
costing 2
then assigned the plant and storage location
organization levels
Plant: -9091
Storage location:-9091
Under heading Basic data:-
Material:- Raw material 9091
Base Unit:- each
Material group:- 004
Under heading Purchase:-
Purchase group: 000
Under heading MRP1:-
MRP type: ND
Under heading MRP 2:-
Planned delivery time : 1day
Under heading Costing1:-
select the column with qty structure
Under heading Accounting:-
Valuation class: 3000
Price control: V
Mvoing price : 100
this much I did and save and I got the error message
If anything more I should configure, please let me know
Thank you
Jomon Mathew