Well! Other idea is to once again review the complete master data set-up. Make sure following master data exisit for Subcontracting:
Eg. If A is header and B is component
1. Procurement Type F-30 in ECC and X in APO for A
2. Subcontracting type Purchasing Info record (PIR) for A
3. Transportation lane "Subcontractor-->Plant" for A. Type of procurement should be Subcontracting. Also maintain Means of Transport.
4. Manually create T lane "Plant-->Subcontractor" for Product B. Also maintain Means of Transport.
5. PDS / PPM at Subcontractor / Vendor location for Product A.
6. Production version maintained for Product A in ECC
7. Same production version is maintained in PIR
8. All the master data and transaction data Integration models are active
9. Distribution definitions are defined in APO
Regards,
Ravi
Message was edited by: Ravi M