HI,
I am a sap new guy.
I wanna know, after planned order was converted to production order,and now BOM changed, we added new materials into production order.
Then we run MRP(material number for order ) by MD02, why new material has no demand ,no PR?
BUT if i run MRP by this new added materials(raw material),it will has demand,why?
I set up MRP control parameters like this 1-3-1-3-2.
Regards
Nemo