MRP for storage locations

$
0
0

Hi,

 

One ROH material is extended to 2 storage locations (A,B). ROH is a BOM component for 2 intermediates.

 

ROH Storage location A - Material Master

ROH Storage location B

 

Each tank cannot go less than 10 tonns and cannot exceed more than 50 tonns


Re order point 25 tonns.

 

Order lot size is 35 tonns.


MRP will consider only one storage location A during requirements generation, becuase material master updated with storage location A only.

My requirement like MRP should consider the both storage locations during MRP run and generate the requirements as per the re order point for inventory.