Backward Scheduling

$
0
0

Hi,

 

I am trying to incorporate fixed duration times and quality testing times in the production models to back up these two times so that we can get production proposals that show when we need to make the product.  Right now, if I put in sales orders for three products that have a fixed duration of 24 hours each due to ship in eleven days, the proposal tells me to make all three batches 10 days from now (apparently the transit time is being factored).  Can anyone help?

 

Thanks,

Shan